Brewpub floor plan: seven things to settle early

Before quoting a brewpub system, settle floor area, three-phase power, water and drainage, steam venting, tank placement, the glycol chiller and routes for malt and kegs.

· 5 min read

Most surprise costs in a restaurant microbrewery come from the site rather than the equipment: floors without fall, too little power, undersized drains. Settling these seven points early keeps the quote realistic and installation quick.

  1. Floor area: roughly 25–40 m² for 100–200 L per batch and 60–100 m² for 300–500 L (indicative, depends on tank count).
  2. Power: three-phase 380 V; the load depends on heating (direct electric or steam boiler).
  3. Water: steady, filtered supply plus hot water for CIP cleaning.
  4. Drainage: stainless trench drains with the floor sloping to them, resistant to hot water and chemicals.
  5. Steam and ventilation: an extraction hood over the kettle, airflow in the fermentation area and around CO2 cylinders.
  6. Tanks and glycol: fermenter positions, a well-ventilated spot for the glycol chiller, short cooling lines.
  7. Access: doors wide enough for vessels and tanks; separate routes for malt in and kegs out.
200L fermenters and glycol chiller on one frame
Fermenters next to the glycol chiller keep cooling lines short and easy to service.
Mobile CIP cart with pump and control box
Leave room and a hot-water supply for the CIP cart that cleans vessels, tanks and lines.

Let guests see the brewhouse: polished stainless is decoration and a "brewed here" promise. Put the bar close to the cold room or keg cabinets so beer lines stay short and foam stays low.

KRS surveys your site and sends a 3D CAD layout with a quote for 300L or 500L systems — reply within 24 working hours.

Request a quote & layout →